Both Fast Tracking and Crashing are concepts of project management to do schedule compression. In fast tracking we make sequential activities at critical path in parallel. It may increase risk factor and rework because we overlook dependencies between activities.
In crashing the resources are...
https://wp.me/p2Z1Hg-E7h
Learn how to use a Run Chart (sometimes called a Control Chart) to help you to measure performance. This is a very simple tool that you can use to search for trends and patterns in your data. Video Rating: / 5 RUN CHART: What is a Run Chart? Video Tutorial This video describes what is a run... https://wp.me/p2Z1Hg-ktm